Fired Heaters

2019-2021

Revamp of cracking Furnace F-1601 C for BOREALIS AB, Stenungsund, Sweden

2018 – 2019

Revamp of cracking Furnace F-1601 D for BOREALIS AB, Stenungsund, Sweden

2016 – 2018

Revamp of cracking Furnace F-1601 E for BOREALIS AB, Stenungsund, Sweden

References can be forwarded upon request.

2019-2020

Fabrication and erection of steel structure and coils of furnace for A602 STACE Project at INEOS Styrolution, Antwerp, Belgium

2018-2019

Fabrication and erection of steel structure and radiant coils of platforming heaters H2301A&B, H2302A&B, H2303 as well as transfer line piping; disassembly of old radiant coils and transfer line piping at PREEM Refinery in Lysekil, Sweden

2015

Prefabrication and supply of steelwork (ducting guillotines, expansion joints and stack damper)

2014

Erection of Hot Oil Heater BA-1852, Borealis Polymers Oy, Porvoo, Finland

2013 – 2014

Fabrication and delivery of Hot Oil Heater BA-1852, Borealis Polymers Oy, Porvoo, Finland

References can be forwarded upon request.

2019 – 2021

Site erection of new fired heater H-1001 and revamp of existing Viscosity Breaking Unit (VBU) during maintenance shut down at TOTAL Refinery in Leuna, Germany

References can be forwarded upon request.

2021

Revamp of Reactor Feed Heater BA-10334 including mechanical works and refractory lining application at NESTE Refinery during TA2021, Porvoo, Finland

References can be forwarded upon request.

2014

Radiant coil prefabrication and convection, flue gas cooler modules for Hot Oil Heater F-9601, DONG Project, Denmark

References can be forwarded upon request