2015
Prefabrication and erection of piping as well as equipment installation for New Oil Catalyst and Donor Feed System, Porvoo, Finland
2014-2015
Prefabrication and erection of piping as well as equipment installation, JCDK Project, Porvoo, Finland
2014-2015
Prefabrication and erection of steel structures and piping as well as equipment installation for Phenol Plant, Porvoo, Finland References can be forwarded
2019-2020
Erection of SWISSCOMBI ecoDry, Steam Heated Evaporator, extension of Compressed Air Unit as well as supply of materials, prefabrication and erection of piping for steam heated evaporator and suport steel structure at BIOAGRA S.A. „GOŚWINOWICE” Ethanol Plant
2018
Supply of materials, prefabrication and erection of piping and steel structure as well as erection of valves and instruments at BIOAGRA S.A. „GOŚWINOWICE” Ethanol Plant References can be forwarded upon request.
2016 – 2018
Prefabrication and erection of piping and steel structure as well as equipment installation, Biopropane Project, Rotterdam, The Netherlands References can be forwarded upon request.
2019-2021
Prefabrication and erection of piping and steel structure, disassembly of old piping as well as installation of equipment at TL2 South NESTE Refinery during TA2021, Porvoo, Finland
2019-2021
Prefabrication and erection of piping and steel structure, disassembly of old piping as well as installation of equipment at TL2 FCC NESTE Refinery during TA2021, Porvoo, Finland
2017
Prefabrication and erection of 64 tons of piping (Mat. P5, P9) from ½” to 10” as well as installation of 50 tons of static&rotary equipment, Hot Sulphuric Lines, Naantali, Finland
2015
Prefabrication and erection of 10 tons of piping and installation of 9 tons of equipment, PHDJ PL3 Unit Revamp 2015, Porvoo, Finland
2014-2015
Modernization of Steam Generating Unit including prefabrication and erection of 79 tons of piping, 15 tons of steel structure, installation of 35 tons of equipment, PHCZ PL3 Porvoo, Finland References can be forwarded upon request.
2016 – 2018
Prefabrication and assembly of pipelines and steel structure and assembly of equipment, Project Biopropane, Rotterdam, The Netherlands
2021-2022
Erection of four complete Claus Systems comprising of Claus burners, thermal reactors, waste heat
boilers, sulphur condensers, steam drums as well as refractory lining application on Claus burners, thermal reactors, sulphur condensers at LOTOS S.A. Refinery in Gdansk
2016 – 2017
Air Liquide Global E&C Solutions Poland S.A. – Prefabrication and erection of piping and erection of static and rotary equipment at Air Separation Unit in Dabrowa Górnicza, ALKAT Renewal Project
2016
Air Liquide Global E&C Solutions France S.A. – Supply of materials, prefabrication and erection of piping and steel structures, exchange of reactors, e&i works and insulation works, Al Heracles Flexicoker revamp project, Rotterdam, the Netherlands References can be forwarded upon request.
2015-2016
Delivery and installation of process piping and erection of air ducts for new heat boiler house, EDF Polska S.A., Kraków Power Plant